January 2008

 Jan2008_MillsCoolingWaterArea    Jan2008_ConcentrateHandlingAndStorage
 Mills Cooling Water Area
 
 Concentrate Handling and Storage
 Jan2008_CleanerFlotationCells    Jan2008_TailingsBridge
 Cleaner Floatation Cells drivers installed
 
 Tailings bridge with rakes ready for installation
 Jan2008_PipeRacks    Jan2008_PlantFromEast
 Pipe racks east west
 
 Plant from east
 Jan08_994F_FELbucket    Jan08_994F_FEL
 994F front end loader - 17m3 bucket
 
994F front end loader next to EH4500s
 Jan08_27CompletedTrucksOnSite    Jan08_Trucks8to13
 All 27 completed trucks now on site
 
 Completed trucks numbered 8 to 13 lined up
 Jan08_DieselShoverlElectricDrive    Jan08_BaseForFirstTrolleyLinePole
 Diesel shovel - electric drive
 
 Base for first trolley line pole
 Jan08_BPFuelFacility    
 BP fuel facility
   

Share Price

Symbol Last Trade $ Change
ASX EQN 3.980 -0.180
TSX EQN 3.81 -0.11

Copper Price

Price (US$/lb) $ Change
3.770 -0.059

ASX and TSX Logos ASX TSX Prices are delayed by at least 20 minutes.
Click a logo to view complete
online share information

Videos

Lumwana Flyover Video 23-May 2008


Contacts

Perth Office

Ground Floor, 50 Kings Park Road
West Perth WA 6005
Tel: +61 (0) 8 9322 3318
Fax: +61 (0) 8 9324 1195

Toronto Office

155 University Avenue, Suite 1701
Toronto, Ontario Canada M5H 3B7
Tel: +1 (416) 865 3393
Fax: +1 (416) 865 3394


Join our mailing list

Click here to join our mailing list and keep up to
date with all the news at Equinox